Dubai has approved a new package of contracts worth AED 56.5 bn ($15.4 bn) for Al Maktoum International Airport at Dubai World Central, pushing the project further into large-scale construction.
His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, Deputy Prime Minister and Minister of Defence, announced the approval on X. He said 14,000 people are now working on the scheme, which aims to deliver the "world's largest and best airport."
The contracts were approved under the directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai. They bring the total value of contracts awarded on the project to more than AED 80 bn.
The new awards expand work across the passenger terminals, concourses, transport infrastructure, power systems and other critical airport facilities.
Sheikh Hamdan said that once fully complete, the airport will be able to handle more than 260 million passengers a year. He added that this will strengthen Dubai's position as a leading global aviation hub and one of the world's most sought-after destinations.
Phase One gathers pace
His Highness Sheikh Ahmed bin Saeed Al Maktoum, Chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), said the project is now in its large-scale construction phase.
"We are moving decisively ahead with Phase One in accordance with the approved programme," he said. He added that the contracts and delivery sequence were designed to keep several sites moving forward at once while maintaining the highest standards of quality and safety.
The current phase includes a second runway, due to open in 2027. The first phase of the new airport is scheduled to open in the early 2030s.
Progress on site
Work is moving quickly across the terminal areas, concourses, tunnels, transport facilities and utility networks. Cumulative working hours on the project have now passed 21.3 million.
DAEP said works in the Concourse 2 and Concourse 3 zones and in the central part of the site are nearing completion. These packages include tunnels for the baggage handling system, routes for ground service equipment and the main baggage handling network.
Enabling works are also continuing in the central passenger terminal zone, which covers the West Terminal, Concourse 1 and the Ground Transportation Centre, as well as in the Concourse 4 area.
Al Maktoum International Airport Dubai World Central